Designing the Programme · lesson 3 of 3

What it actually costs

After this lesson you can

Give an honest estimate of effort and money for an authentication programme.

Assumes you have read The work that is not yours.

Asked how long this takes, the honest answer has two parts: the work is small, and the elapsed time is not, because most of it is waiting for evidence and for other people.

Effort against elapsed time

PhaseEffortElapsed
Publish reporting across the estateA dayA day
Protect non-sending domainsA day, generatedA day, plus a fortnight of confirmation
Read reports, build the sender inventoryA few hours a weekFour weeks minimum, a quarter if seasonal
Align each third-party senderAn hour of your time eachWeeks each, in parallel, gated on the vendor
Move to quarantine, observe, move to rejectAn hour per stepEight weeks, and not compressible
Total for a primary domainTwo to three weeks of workOne to two quarters

The gap between those columns is the entire management problem. Two weeks of effort spread over two quarters reads as inactivity to anyone tracking it by the week, which is why the waiting periods have to be stated as plan items rather than as delays.

Money

  • Reporting: free to low. A mailbox costs nothing. A processor is a modest annual subscription and saves real time on a large estate.
  • Vendor tier upgrades: the real cost, and unpredictable. A platform that gates custom return-path or customer-domain DKIM behind an enterprise tier can cost more than everything else combined.
  • MTA-STS: a certificate and a static host. Effectively free if you already run web infrastructure.
  • BIMI: hundreds to thousands annually, plus a trademark you may not have. This is the one line item worth challenging.

What to say when asked for a date

"Reporting is live this week, and forty parked domains
 are protected by Friday. The primary domain reaches
 quarantine in about eight weeks and reject about eight
 weeks after that — assuming the marketing platform can
 align on our current contract, which I'll know by
 Thursday. If it can't, that date moves to the renewal."

The dependency is the estimate

A date given without naming what it rests on will be treated as a commitment and missed. Naming the single vendor that determines it converts a missed date into a known contract decision, which is somebody else’s to make and far easier to escalate.